Reply To: Cross dependency impact Dashboard in MS Project

Home Forums Discussion Cross dependency impact Dashboard in MS Project Reply To: Cross dependency impact Dashboard in MS Project

#411148
Jigs Gaton
Member
  • Author
  • Forum Pro

Well, for problem #1 above, you might find the add-in Pathfinder helpful for identifying (filtering) on predecessors and successors, or you have to write your own macro for that.

For problem # 2 above, yes, status indicators such as a RAG indicator formula can be put into a custom field, and then you add that custom field to the Global.Mpt using the Organizer, and then add that to a column in the master plan, and you will see the indicator in both the master plan and subproject rows when undisclosed.

Hope that helps!
Jigs