Reply To: Cross dependency impact Dashboard in MS Project

Home Forums Discussion Cross dependency impact Dashboard in MS Project Reply To: Cross dependency impact Dashboard in MS Project

#411149

Thanks a lot! Jigs,

Got a macro that works perfectly to filter out dependent tasks within a subproject. As I am using this in Master Project dependency will appear as a path to the other file and the macro is not working.

Following is the code used. Is there any solution to this problem
Sub DefinePath()

Dim T As Task
Dim I As Long

‘Clear the existing filter
Application.FilterClear

‘Capture the selected task
I = Application.ActiveCell.Task.UniqueID

‘Flag the Predecessors and Successors
For Each T In ActiveProject.Tasks
T.Text10 = “”
If T.UniqueID = I Then
T.Text10 = “Selected Task”
End If
If T.PathPredecessor = True Then
T.Text10 = “Predecessor”
End If
If T.PathSuccessor = True Then
T.Text10 = “Successor”
End If
Next T

‘Apply a filter on the flagged tasks
SetAutoFilter FieldName:=”Text10″, FilterType:=pjAutoFilterIn, _
Criteria1:=”Predecessor” & Chr$(9) & “Successor” & Chr$(9) & “Selected Task”

End Sub