Gopika,
Your macro is based on Task Path. Does the Task Path bar highlighter work across subprojects? If so, then your macro “should” work. (I can’t test because I’m on MSP 2010).
If Task Path isn’t working across subprojects, then you’ll need a logic-tracing add-in. Look for Pathfinder, ProjectProCorp, projectwidgets.com, Opdec, or BPC Logic Filter. (The last is one my company developed for internal use, but we do share it.)