Loading...
Quick Links

Reply To: Project defaults certain tasks to 100% when a lower percent complete is entered.

Home Forums Discussion Project defaults certain tasks to 100% when a lower percent complete is entered. Reply To: Project defaults certain tasks to 100% when a lower percent complete is entered.

#411229
D Robert
Guest

I just encountered the same issue in MS Project Standard 2013. Using Howard’s suggestion, the issue was resolved. However, changing from “Fixed Duration” and back again was not necessary.