Eric Uyttewaal
Participant

Michael,

I have seen all problems you describe; here are my work arounds:
– For the lack of recalculation, I have gotten into the habit of pressing F9 to force instant recalculation, which solves most situations for me when the scheduling engine did not. Microsoft has certainly left some open-ends in their code where a recalculation should be triggered but because of their omission none is.
– For the cutting/copying and pasting and getting circular message: I have found that this message is true but hard to understand, so this one is not Microsoft`s omission, it is your omission. To give you one of many examples where this could happen: if you cut a task that is a predecessor to a summary task and paste it into the detail tasks of the summary task you have created circular logic.

I hope this helps…

Eric