Reply To: Using different work weeks in one schedule

Home Forums Discussion Using different work weeks in one schedule Reply To: Using different work weeks in one schedule

#411324
Dave Howe
Member

Thanks, Thomas. The way you describe it is what I would expect to happen. Once copied and pasted and applying the 4dX10h task calendar to the pasted task, I’d expect to see a duration of 5 days, starting on Monday and Finishing on Thursday. However, what happens is it finishes the following Monday.

Original contractor schedule using 4dX10h calendar:
40 hour task, duration = 4 days, starts Monday 12/4, finishes Thursday 12/7

copied and pasted task to new schedule using standard calendar, but applied contractor calendar to pasted task:
40 hour task, duration = 5 days, starts Monday 12/4, finishes Monday 12/11

Any idea why that is happening?