Hi, Looks like the local view formatting is overwritten either from enterprise view or by applying some bar style format on the gantt chart.
Please share information to reproduce this issue such as
1. Is this behavior displayed by all files in Project Server 2013?
2. Is there custom code/macro on the file displaying this behavior?
3. Did you use the existing view to customize the bar style format or did you create a new view?