Larry Christofaro
Participant

A couple of obvious questions to start. Did you create a status date, and if so is it the day before the current date? The status date line shows at the end of the day vs. today’s date that shows in the beginning, and can overlap the status date if they conflict. It’s also only for the view you set it for, not all views. Hope that helps.