Reply To: Help with VBA Formula for Status Colors

Home Forums Discussion Help with VBA Formula for Status Colors Reply To: Help with VBA Formula for Status Colors

#411708
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Lookng at the format of the code with _ at the end of each line, you are using this code in VBA. ProjDateValue works only in custom field formula. Replace (IIf(([Baseline Finish] = ProjDateValue(“NA”)), 9) with (IIf(([Baseline Finish] = “NA”), 9)