Reply To: MS Project 2013 exporting to Excel 2013

Home Forums Discussion MS Project 2013 exporting to Excel 2013 Reply To: MS Project 2013 exporting to Excel 2013

#411816
Thomas Boyle
Guest

Hillary,
The information you want is included in the assignments table, not the tasks table.

When the Export Wizard asks you to “Select the types of data you want to export,” just stick with “Tasks,” but be sure to check the box lower down for “Include assignment rows in output.” That should give you the mixed-data report that you seek. You’ll have to pay attention to the data field mapping.

Alternatively, I would include all three data tables, then combine them in Excel to get the report I want.