Maureen, as mentioned above, Q1 and Q2 can best be addressed by project server, but I’ve written an article here on MPUG that might help if you are all MS Project 2016 standalone users: https://www.mpug.com/articles/pmo-in-a-box/. This article addresses all three of your questions I believe. The elephant in the room is access control, as there really is none to speak of, outside of self control and what say Dropbox does when two users try and save the same open file: a conflict file is created that must be sorted out manually later. Hope this helps!
Jigs