Reply To: The enterprise global already contains a view named \"No Group\".

Home Forums Discussion The enterprise global already contains a view named \"No Group\". Reply To: The enterprise global already contains a view named \"No Group\".

#411928
Dave Howe
Member

Thanks, Larry. Correct, the view in question was called “No Group”. Oddly, it was only happening on one project and a couple people, but not to me. Instead of clicking “replace” like I mentioned we did in my original post, I have since selected “rename” the duplicate “No Group” views, then delete them, “Save As” locally, then replace the enterprise project with the local version. So far, that seems to have eliminated the issue, but still a mystery as to what the root cause was. Thanks!