Loading...
Quick Links

Reply To: MSP2016 Fixed Duration Task change work doesn't recalc assigned resource units

Home Forums Discussion MSP2016 Fixed Duration Task change work doesn't recalc assigned resource units Reply To: MSP2016 Fixed Duration Task change work doesn't recalc assigned resource units

#412063
Larry Christofaro
Participant

Dear member, that’s a good question of which the answer has changed in a recent update (not sure if it was 2016 or 2013). The Units field used to represent the Peak units, but was changed to represent the Assignment units. If you go to the Resource Usage view you can see both. There are some nice up sides to this change, but one of the down sides is that the display doesn’t always reflect what is going on with the Work column in the Gantt chart. There have been a lot of blogs on this topic if you are interested in more or still have questions. Good luck…