Loading...
Quick Links

Reply To: MSP2016 Fixed Duration Task change work doesn't recalc assigned resource units

Home Forums Discussion MSP2016 Fixed Duration Task change work doesn't recalc assigned resource units Reply To: MSP2016 Fixed Duration Task change work doesn't recalc assigned resource units

#412081
André Stolk
Guest

Clear to me Daryl! Indeed a good suggestion to use a resource usage view with columns for Max Units on the resource level, Assignment Units and Peak, and analyze the exceedings of Assignment Units compared to Max Units and Peak compared to Assignment Units.
Thanks again!