Reply To: How to make a task start x days before the deadline….?

Home Forums Discussion How to make a task start x days before the deadline….? Reply To: How to make a task start x days before the deadline….?

#412189

Kennet;
Slight correction.
Set up the deadline milestone as indicated. Then set up the task as a predecessor to the milestone with a positive lag value. Sorry about that.