Hi Jigs

I did not explain my issue correctly:

I have a master project with 100 activities/tasks with a milestone task of conclusion.

Later i insert a small subproject (5 tasks)

I would like to have dependencies between the last task of my master project and my subproject summary task.

Then if i track the tasks of master project will have automatically impact on the subproject inserted.

Other way How can i constraint (start and finish) the subproject with the master project?

Regards,

Carlos Santos