#412328
Larry Christofaro
Participant

Roger, unfortunately I don’t believe there is anything you can do to a single resource with different availability to two different projects, at least not at the resource level. You might be able to solve this by creating a task calendar on the one project that can only work in the morning. Pros and cons, but hopefully this can help.