Reply To: Resource pool and personal calendars

Home Forums Discussion Resource pool and personal calendars Reply To: Resource pool and personal calendars

#412330
Roger Heirbaut
Guest

Hi Larry, working with a task calendar is indeed a valid possibility in a simple situation, but that wouldn’t work if there is more than 1 resource allocated to that task and that other resource(s) is working on ‘normal’ hours