Kennet
I’m not sure I’m clear on what you mean by “Project can’t level…”. Are you getting error messages during the leveling process?
Can you provide more details.
One thing I will add, is that specific task types can negate leveling. Rather than trying to explain it here, I’m going to suggest the following article. I know the author so I think he’ll be OK with me referencing it. 🙂
https://www.mpug.com/articles/resource-leveling-leveling-hierarchy-part-1/
There is a part II to that article coving the rest of the leveling hierarchy and in both articles, examples of scenarios are provided that illustrate how project might not actually level specific tasks.
And BTW, these are part of a 13 article series on leveling also accompanied with 2, 1 hour webinars if you want to dig a lot deeper into leveling.
Feel free to provide more details on “Project can’t level”.