Reply To: Leveling – ….cannot resolve the overallocation of ….

Home Forums Discussion Leveling – ….cannot resolve the overallocation of …. Reply To: Leveling – ….cannot resolve the overallocation of ….

#412401

Daryl

Sorry if I didnt explain myself clearly enough. YES, I´m getting an error message when during the leveling process. The message says: “Project cannot solve the overallocation of “Ole” on Tue 01-05-2018″

So, I get an error message during the leveling process when the timeframe is set to “week by week” and I dont get an error message during the leveling process when I change the timeframe to “Minute by minute”

I´m very well familiar with your 13 articles about the leveling process. Much appreciated by the way 🙂

Kennet