Jan, there is a difference between the task custom fields you setup in Project and the Enterprise Task custom fields that are setup using PWA. Project task fields are for each project. PWA task custom fields are for all projects. Try that and see if that works for you.

Note that we are talking task custom fields, not project level custom fields. Hope it helps…