Reply To: Progress line against baseline 1

Home Forums Discussion Progress line against baseline 1 Reply To: Progress line against baseline 1

#412564
Larry Christofaro
Participant

Adam, I didn’t see any option to set which baseline to use for the progress bar. I suggest, which I teach as best practice, to always use Baseline as your current baseline. Then use Baseline1-10 for historical baselines. All variance fields and views use Baseline and it is easier to use those as is then creating all your own calculations. You can use the Set Interim Plan to copy baselines (IE: copy Baseline to Baseline2, then Baseline1 to Baseline, then Baseline2 to Baseline1). Then use Clear Baseline to clear Baseline2. hope that helps…