Reply To: Resource Groups and Team Resources

Home Forums Discussion Resource Groups and Team Resources Reply To: Resource Groups and Team Resources

#412565
Larry Christofaro
Participant

Hi Gopika. There’s a lot of information online that can provide details about groups and team resources, but I’ll try to give you a quick comparison to start. Think of Groups as a resource utilization function for rolling up like resources. Team Resource Pools is a way for team members to assign themselves to a task. They certainly have similarities, but Microsoft configures the two for different purposes. Hope that helps…