Reply To: Project 2016: How to set consistent overtime across all resources?

Home Forums Discussion Project 2016: How to set consistent overtime across all resources? Reply To: Project 2016: How to set consistent overtime across all resources?

#412743
Larry ChristofaroLarry Christofaro
Participant

Sabina, you need to do two things to setup a 9 hour/day calendar. (1) change the Standard calendar to a 9 hour workday (Project ribbon, Change Working Time, Select Standard calendar, go to the Work Weeks tab, select Monday-Friday and set the hours accordingly). (2) select the Options button on the bottom of that page and set the Default start/end times, Hours per day, and Hours per week to match. Hope that helps.