Home › Forums › Discussion › Adding Current Date into a MS Project Report › Reply To: Adding Current Date into a MS Project Report
As you found out, current date is not available out of the box. The only way I can think of is to create a custom task field called Current Date with the formula [Current Date]. Then create a one field table at the project level with that field. Hope that helps…