Reply To: Gantt bars size issue

Home Forums Discussion Gantt bars size issue Reply To: Gantt bars size issue

#412788
Larry Christofaro
Participant

Sebastien. I’ve not heard of that before but try taking a look at the bar layout. (Format ribbon, Layout). The layout menu has a bar height option that defaults to 12 in my version (Project 2016). If the differences are in the same project then that’s not the solution and I don’t have an answer.