Reply To: Resource Leveling w/ Master Schedule & Sub-Projects & a Shared Resource Pool

Home Forums Discussion Resource Leveling w/ Master Schedule & Sub-Projects & a Shared Resource Pool Reply To: Resource Leveling w/ Master Schedule & Sub-Projects & a Shared Resource Pool

#412819
Larry ChristofaroLarry Christofaro
Participant

Robert, that’s a complex question that could be one or more of many causes:
1. I assume all projects including the resource pool are open when resource leveling
2. Do your projects all have the same priority? Project priority defaults to 500, which will then prioritize by tasks across all projects.
3. Is “Leveling can adjust individual assignments on a task” selected and are there multiple resources assigned to the task in question.
4. Check the predecessors on the two tasks. They don’t have to be predecessors to each other to have Project assign lower priorities first.
5. Do you have Leveling Order set to Priority/Standard? That’s a must.
That’s at least a start to check. Hope that helps…