Loading...
Quick Links

Reply To: Resource Leveling w/ Master Schedule & Sub-Projects & a Shared Resource Pool

Home Forums Discussion Resource Leveling w/ Master Schedule & Sub-Projects & a Shared Resource Pool Reply To: Resource Leveling w/ Master Schedule & Sub-Projects & a Shared Resource Pool

#412823

Hi Larry,
Thanks for the answer. I did have all the sub-projects open while leveling and all have a priority. I have assigned only one person to each task. Generally, that’s the way we operate, anyway. I went through the entire list of projects this morning and scrubbed the predecessors for each task. This still allowed a task to begin with the first few days have “0” labor hours. I’m not that experienced with project — but have never seen that before. Finally, I turned off leveling’s ability to create splits. That worked… I just don’t understand why.