Reply To: VBA reporting on time phased data / projects sharing a common resource file

Home Forums Discussion VBA reporting on time phased data / projects sharing a common resource file Reply To: VBA reporting on time phased data / projects sharing a common resource file

#412896

All,
I’ve worked through this and found that walking through the time phased data with VB will not work if your project shares resources. I don’t understand why, though. My workaround: save a copy of the file to another directory. Open the copy but decline to open the shared resources file. Then, once open, change the resources to use those that are local. A little time consuming… but if you’re creating a report spanning more than a project or two, you’ll still save time.

Mark