Reply To: Master – Sub Projects Date Constraint Concern (MS Project 2016)

Home Forums Discussion Master – Sub Projects Date Constraint Concern (MS Project 2016) Reply To: Master – Sub Projects Date Constraint Concern (MS Project 2016)

#412922
Larry ChristofaroLarry Christofaro
Participant

I agree with Jigs. Another thought, if you are changing a sub-project task in your master project, you are actually changing the sub-project. Setting a start date directly will always set a Start no earlier than constraint. That’s how Project knows to keep the task on that date.