Reply To: Enterprise Resource Pool with Project Professional 2016

Home Forums Discussion Enterprise Resource Pool with Project Professional 2016 Reply To: Enterprise Resource Pool with Project Professional 2016

#412951
Larry Christofaro
Participant

When using Project Server, you can set the “Load Summary Resource Assignments” to yes and it will show other project commitments. You may need to go to Configure Accounts (File / Info / Manage Accounts) and set the When Starting to “Choose and account”. I just tried this with Project Online and it didn’t work for me, but it did with Project Server. That I’m not sure what happened and if it got deprecated or not. You can also see the assignments in a Resource Usage view. Hope that helps…