Home › Forums › Discussion › Project Online: Actual work varies based on view › Reply To: Project Online: Actual work varies based on view
Shauna, take a look at the end date of the assignment If it is earlier than the timesheet date, try using either the Move remaining work option or changing the Resume date to move remaining work to current. This is a pretty normal standard practice for PMs to do each period.