Reply To: Project Online: Actual work varies based on view

Home Forums Discussion Project Online: Actual work varies based on view Reply To: Project Online: Actual work varies based on view

#412999
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Shauna – Tasks page is to record the task progress, which gets reflected in the schedule. Timesheet page is to record the time spent on each task. It is not necessary that hours entered in Task page and Timesheet needs to match. If you want task progress and time to entered in the same page, you need to turn on Single Entry mode (https://support.office.com/en-us/article/overview-enter-time-and-task-progress-in-one-view-8fab9585-8607-44bb-ba9a-abb696a17b24#__toc286059312)