Reply To: exporting tasks to Outlook

Home Forums Discussion exporting tasks to Outlook Reply To: exporting tasks to Outlook

#413036
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Project 2016 does not have this feature. Sync to outlook feature is part of Project Server/Online. You need either install paid add-in from partners or the steps in https://www.mpug.com/articles/integrating-project-and-outlook/