Reply To: Resource Task List Sorted By Start Date

Home Forums Discussion Resource Task List Sorted By Start Date Reply To: Resource Task List Sorted By Start Date

#413088
Larry Christofaro
Participant

The out of the box view designed for this is the Resource Assignment view. It is a ribbon option on the Resources page. Select a resource(s) and then select Resource Assignment. You can also create views with filters or create a resource view by manager to simplify the process. Hope that helps.