Loading...
Quick Links

Reply To: Main summary task Status is not calculating correctly – Project 2016

Home Forums Discussion Main summary task Status is not calculating correctly – Project 2016 Reply To: Main summary task Status is not calculating correctly – Project 2016

#413099

Deepa
Summary tasks will not contain accurate “roll up” information if the summary task is set to manual scheduled. Change the summary task to Auto Scheduled and the values should then align.