Reply To: Update Bar-Format for a Task After a Specified Date

Home Forums Discussion Update Bar-Format for a Task After a Specified Date Reply To: Update Bar-Format for a Task After a Specified Date

#413105

Perry
If memory serves (I Can’t remember where I found this nugget), the bar formatting applied is based on the first formatting row that matches. So if Row 1 is for an active task to display blue and row 2 is for active tasks with a special code to display red, I believe row 1 takes precedence because the process stops on the first formatting row where a true condition is found.
You might try moving the row defining your custom format up in the sequence (cut/Paste) so it becomes the first true value found. I’m also assuming you have some unique condition your checking such as a custom field with value in it, or it’s a late task for example.
Hope that helps