Deepa;
I did some digging in MS Project 2013 help (the version I’m running) and found this definition of how “Late” is identified.

“If the timephased cumulative percent complete does not reach midnight on the day before the status date, then the Status field contains Late.”
So this is basically earned value and another way of saying that if the completed work is not equal to or greater than the planned completed work on the status date, then the task is behind.

Since you indicated you have no resources assigned, is it possible that your Status Date is a future date?