Thanks Daryl. But my status date is set to July 20th. And here are the task. Al my sub tasks are either completed or future tas. Summary still says it is late
Outline Number Task Mode Task Start Finish % Complete Status
1.2.3 Auto Scheduled Wed 5/16/18 Fri 11/30/18 42% Late
1.2.3.1 Auto Scheduled Wed 5/16/18 Wed 5/16/18 100% Complete
1.2.3.2 Auto Scheduled Fri 8/31/18 Fri 8/31/18 0% Future Task
1.2.3.3 Auto Scheduled Fri 8/31/18 Fri 8/31/18 0% Future Task
1.2.3.4 Auto Scheduled Wed 5/16/18 Fri 11/30/18 44% On Schedule
1.2.3.4.1 Auto Scheduled Wed 5/16/18 Wed 5/16/18 100% Complete
1.2.3.4.2 Auto Scheduled Wed 5/16/18 Wed 5/16/18 100% Complete
1.2.3.4.3 Auto Scheduled Wed 5/16/18 Wed 5/16/18 100% Complete
1.2.3.4.4 Auto Scheduled Thu 7/12/18 Thu 7/12/18 100% Complete
1.2.3.4.5 Auto Scheduled Fri 7/27/18 Fri 7/27/18 0% Future Task
1.2.3.4.6 Auto Scheduled Fri 7/27/18 Fri 7/27/18 0% Future Task
1.2.3.4.7 Auto Scheduled Fri 8/31/18 Fri 8/31/18 0% Future Task
1.2.3.4.8 Auto Scheduled Fri 11/30/18 Fri 11/30/18 0% Future Task
1.2.3.4.9 Auto Scheduled Fri 7/27/18 Fri 7/27/18 0% Future Task