Hi Ramses,
I’d think the cause of this is a difference in project status dates. The status date determines how the individual task STATUS field is set (Late, On Schedule, Future). Also, the summary task Status field is determined by the underlying sub tasks. Meaning, it sort of averages the sub-task status.