Reply To: Scheduling from constraint date when the constraint date is half way through the

Home Forums Discussion Scheduling from constraint date when the constraint date is half way through the Reply To: Scheduling from constraint date when the constraint date is half way through the

#413256
Larry Christofaro
Participant

I agree with Sai and especially Heather. But to follow up with Daryl’s idea, you could give backward scheduling / as late as possible a test and determine if it provides a value. If it does, set one of your baselines, then resort back to a forward schedule. That baseline could give you valuable information on where you are to your deadline. Hmmm, on another thought, you could also use Free Slack / Total slack and Late Start to determine how much contingency you have to your deadline. You could even setup a special Gantt format that uses Late Start / Late Finish. Anyway, some additional thoughts to try and see if something works for you. Project usually has multiple options and lets the user figure out what option has the best effort / value. Good luck…