Reply To: counting the number of predecessors

Home Forums Discussion counting the number of predecessors Reply To: counting the number of predecessors

#413297
Minerva Goree
Guest

Below is the formula that worked for me. I’m using MSP Server 2016.

IIf(LEN([Predecessors])>0,LEN([Predecessors])-LEN(REPLACE([Predecessors],',',""))+1,0)