Home Forums Discussion About tracking project progress in MS2016 Reply To: About tracking project progress in MS2016

#413336
Larry Christofaro
Participant

Hi Luca. Unfortunately % Complete isn’t something that provides a timephased view. You two sets of fields that provide a timephased analysis are the Cumulative and Earned Value fields. Not sure either of them are what you are looking for. Maybe someone has another thought, but that’s my understanding.