Hello Kerry,
I tried to reproduce your situation, but failed. I created a new task in a new project schedule and entered the Start and Duration. I switched the task to Automatically scheduled and set the Task Type to Fixed Duration. I assigned a resource and modified the Work. Work is evenly distributed when I check it in the Task Usage view.
Maybe your resource has a specific calendar?
Best Regards,
Marcel