Loading...
Quick Links

Reply To: MSP2016 Fixed Duration Task change work doesn't recalc assigned resource units

Home Forums Discussion MSP2016 Fixed Duration Task change work doesn't recalc assigned resource units Reply To: MSP2016 Fixed Duration Task change work doesn't recalc assigned resource units

#413490
Shrikant
Guest

Hi, In my Project; changing work is not reflecting for change in duration though the task type is Fixed Work. I am using MSP2016 and have come across this issue just today.

Thanks, Shrikant