Robert, tracking what happened is always difficult but I suspect that a project got renamed somehow and that the previous project name is still being referenced in the resource pool. If the project doesn’t exist and shouldn’t, go to the resource pool in edit mode, go to the Resource Pool / Share Resources option, then select and break the link. Hope that helps.