Home › Forums › Discussion › Resource allocation questions › Reply To: Resource allocation questions
TJ, I apologize for the confusion. I use resource leveling by default and can’t imagine managing a large project/program any other way. Task Type and Effort Driven matters when you assign resources, as long as you aren’t using fixed duration (in my experience). Leveling works the same no matter Type/Effort Driven. If you are comfortable with Fixed Work then use it. Fixed Units / not Effort Driven gives me more control on how I assign resources, at least in more scenarios than Fixed Work.
Keep doing what you’re doing. My main point is to use the split screen to solve the scenario you mention above. Hope that helps…