Uzma, good question but no one answer. It’s more about organization than timeline, although timeline is typically a consideration. Best practice might say to organize your tasks by phase or deliverable, or a combination of both. In your case you mention departments, which I’ve also seen. Use summary tasks for organization, with levels to be able to drill down to key work packages. It’s all about what you are creating. Within a summary task it is typical to list the tasks by date…but no hard rules. Hope that helps…