Larry,

That is the way we started to attack this and it became unsustainable as there are only 25 rows per cost rate table. So after 5 years (using each of the 5 tabs) we would have to go back to cost rate table A and update which would cause all projects over 5 year old to become incorrect. If we had more than 25 rows per cost rate table, this would be a workable solution.