Reply To: Notify team members that prereqs for their tasks are complete?

Home Forums Discussion Notify team members that prereqs for their tasks are complete? Reply To: Notify team members that prereqs for their tasks are complete?

#413614

I’ve written a VB script that tags each task based on whether the task is “ready to start” or “is underway”. You should be able to update this and send an email based on the “ready to start” tag. I execute the script weekly as I update my projects. I use MSP 2016 desktop Professional. No on-line and no server. I’d be happy to share…

Mark